Severn Bridge HGV ban: new order, but January reopening still on track

You can read this article in 4 minutes

A fresh order keeping goods vehicles over 7.5 tonnes off the westbound M48 approach to the Severn Bridge is due to take effect on 26 November. However, hauliers have been told the legal extension does not mean a further delay to the planned return of heavy lorries in January 2027.

There is a person behind this text – not artificial intelligence. This material was entirely prepared by the editor, using their knowledge and experience.

Key points:

  • The temporary order covers the westbound M48 between Junction 1 and the bridge, including the entry slip road.
  • Affected goods vehicles must use the M4 Prince of Wales Bridge.
  • The order has a maximum legal duration of 18 months, but January 2027 remains the reopening target.
  • A system controlling HGV access is being installed to prevent excessive loading of the crossing.

What changes on 26 November

The National Highways statutory notice sets out a temporary prohibition covering the westbound carriageway from Junction 1 at Aust to the Severn Bridge, together with the junction’s westbound entry slip road. It applies to goods vehicles exceeding 7.5 tonnes, with exemptions for emergency service and maintenance vehicles.

The notice says the measure is required because of the likelihood of danger to the public or serious damage to the road. It gives 26 November 2026 as the commencement date and allows a maximum duration of 18 months. Traffic signs will indicate the restriction.

For operators, the crucial distinction is between that legal period and the programme for restoring access. An order’s maximum lifespan does not establish how long the current operating arrangements will actually be needed.

January remains the target

The Road Haulage Association addressed that distinction in its 14 November update. It said National Highways still expected vehicles over 7.5 tonnes to return in January 2027. According to the association, the order extension is procedural, aligning regulations on both sides of the Severn before the new arrangements begin.

National Highways’ October and November newsletter says construction of the medium-term solution is under way, with testing and mobilisation on track for the end of January. It also reports continued work on the legal powers and technology needed to operate the system.

The newsletter describes ducting, cabinet installation, cabling, connections, signs and paving among the remaining activities. It says Avon and Somerset Police and Gwent Police are involved in discussions about enforcement. A separate long-term feasibility study is examining strengthening options and how future works might be delivered.

Why heavy lorries are being diverted

National Highways introduced the bridge’s existing weight restriction on 27 May 2025 after surveys found deterioration in the main suspension cables. Removing the heaviest goods vehicles reduces loading while keeping the crossing available to other traffic.

The planned replacement system would send HGVs off the motorway at Junction 1 westbound and Junction 2 eastbound, then regulate their return through signals on the entry slips. The aim is to space lorries across the structure rather than allow them to cluster together.

Until those arrangements start, affected HGVs must use the M4 Prince of Wales Bridge. National Highways describes the normal diversion as 14 miles. For an unplanned closure of that bridge, it identifies an alternative via the M5 and M50 of approximately 100 miles.

Local deliveries need particular attention

The Welsh Government’s existing traffic order notice also explains the route for heavy vehicles heading towards Chepstow and the Wye Valley. After using the M4 crossing towards Wales, they should exit and rejoin at Junction 23a, Magor, before returning along the eastbound M48 towards Newhouse.

That routing matters for deliveries close to the original crossing, where a short geographical distance can still require a substantial motorway detour. Dispatchers should therefore check the whole approach to a customer’s premises when reviewing journey plans.

There is also disruption elsewhere on the network. The National Highways newsletter lists closure of the M4 westbound Junction 20 link to the M5 northbound until 4 December 2026, followed by planned works affecting the opposite interchange movement from 13 December to 19 February 2027.

Those works underline the need to check current restrictions on both sides of the estuary. For now, the message is unchanged: the November order continues the HGV restriction, while January remains a target dependent on completing and commissioning the new access system.